CONSTRUCTION: WHAT TO EXPECT
Construction is the main event of any renovation project, and a lot unfolds in a very deliberate sequence. During the process, it’s important to be aware of how the scope of work, design details, and product selections are finalized. Because of the complex coordination involved across many trades and suppliers, endeavour to be as nimble and decisive as possible. Doing so will help keep things moving smoothly.
Below is a typical construction progress checklist. We use this tool to properly coordinate the many reviews and decisions required. To aid us, we establish a regular site meeting (usually bi-weekly) with the contractor, architect, and homeowners. We follow up on each one with a field report to make note of important observations, new action items, and key decisions. Please be sure to read these as they are issued to be help confirm their accuracy and understand your responsibilities.
Regarding billing: each contractor works differently, but most builders invoice biweekly or monthly. With a cost-plus contract, you should expect to see the receipts for every item billed. Regardless, every invoice is an opportunity to check how a project is tracking against its budget. At the start of a construction, it’s always a good idea to have a contingency fund in place to help absorb unforeseen costs (typically around 10%). If a project progresses without tapping into this reserve, you might elect to upgrade towards nicer product selections. Keep in mind, however, that changes in the scope of work which are out of sequence will likely cause redundant costs and time delays.
CONSTRUCTION PROGRESS CHECKLIST
CONSTRUCTION KICK-OFF
Designate construction limit (area of adjacent yards or outbuildings that the contractor will make use of and will likely require re-landscaping by Owner).
Plants to be temporarily moved by Owner or protected by Contractor
Establish tree protection if required
Identify finishes & existing fixtures, etc. that require protection
Establish a regular site meeting time
DEMOLITION
Confirm structural assumptions
Confirm if existing subfloor is suitable for new finishes
Identify repairs needed or major scope changes
Schedule soils test
Review foundation layout
Arrange for structural engineer inspection as required
Review in-slab Plumbing layout
Product Selections: windows and patio doors, integrated plumbing fixtures (bathtub, medicine cabinets, shower controls, toilet, wall-mounted faucets), and fireplace
FRAMING
Review framing layout (especially origin points, dimensions to hold, and critical HVAC or plumbing integration)
Review floor and ceiling structure: stair/access hatch openings & beam locations, etc.
Review eaves and skylights
Check framing: walls and openings (doors and windows, etc.)
Product Selections: roofing, appliances, remaining plumbing fixtures (except accessories can wait if necessary), pre-finished siding, doors (interior and front entry), and door hardware
PLUMBING & HVAC (ROUGH)
Review plumbing waste line paths: any conflicts with design, unexpected bulkheads, pack-outs?
Confirm plumbing fixture heights (especially at showers/tubs)
Identify areas of accessory framing and blocking: towel bars, grab bars, medicine cabinets, mirrors
Confirm equipment placement
Review HVAC ductwork and register locations
Will be an AV/IT installer? If so, schedule their work
BACK-FRAMING & BUILT-INS
Back-Framing: identify any changes to plan or reflected ceiling plan to accommodate unexpected bulkheads, pack-outs, etc.
Confirm stair design and quote
Millwork Shop Drawings: can finishes be roughed-in for early site measurements to enable millwork production?
Send any changes to millworker ahead of their shop drawings
ELECTRICAL (ROUGH)
Coordinate with special AV/IT installer
Confirm panel location
Sconce heights: provide if selections have been made (possibly can be finalized after drywall installation)
Electrical box review (schedule before wiring)
Product Selections: tiles, wood flooring, wallpaper, paint/stain colours for mock-ups (drywall and millwork), decorative light fixtures, bath accessories
ENVELOPE
Review exterior assembly
Check that insulation and vapour barrier have been installed as specified and to create continuous barriers
Exterior Trim & Siding: confirm profiles and identify tricky spots
DRYWALL, PAINT, & TRIM
Check that the correct drywall has been installed based on the finishes to go over them
Review paint selections mock-up
Issue paint schedule
Interior Trim: confirm profiles and identify tricky spots
CUSTOM BUILT-INS, EXTERIOR DETAILS, & FINAL PRODUCT SELECTIONS
Millwork: review shop drawings
Millwork: review finish samples
Deck/Terrace/Porch details: review and confirm design
Product Selections: cabinet hardware, counters & stone slabs, remaining paint/stain colours, rainwater goods, wood floor stain (unless using pre-finished flooring), exterior paving stones
FINISH INSTALLATION
Confirm move-in date
Tile: review layout, trim, and select grout colour
Counter: review overhang & profile
Electrical devices: confirm models and wall plates
Check HVAC finish installation
Decorative hardware: confirm locations
Make punch list (typically about a month after move-in)